U.S. Options
Nasdaq Options Market (NOM) Exchange Replatform
Harmonizing operational and technological processes to provide cutting-edge exchange technology around the globe.
Readiness Milestone | Milestone Date |
|---|---|
| Test Environment (NTF) -Customer Ports Requests Available | March 30, 2026 |
| Customer Test Environment Ready for Testing | April 6, 2026 |
| Production-Customer Ports Requests Available | May 18, 2026 |
| Production Simulation Environment Available | May 25, 2026 |
| 1st Customer Production Test | June 6, 2026 |
| 2nd Customer Production Test | July 11, 2026 |
| Final Confidence Test | July 25, 2026 |
| Symbol Migration Begins | July 27, 2026 |
| Symbol Migration Completes | August 10, 2026 |