Markets

UPDATE: Barrick Gold Down 2% on TSX After Posting Q2; May Reflect Higher Capital Costs

Barrick Gold Corp. (ABX.TO) is down more than 1% on the TSX despite what appears to be a strong Q2. The decline may reflect higher capital costs for certain projects.

Barrick said reported net earnings for Q2 rose 35% to US$1.2 billion (US$1.16 per share) from US$859 million in the prior year period. Q2 adjusted net earnings increased 36% to a record US$1.1 billion (US$1.12 per share) from US$824 million ($0.84 per share) in Q2 2010, reflecting higher realized gold and copper prices and higher gold sales volumes, resulting in an annualized return on equity of about 21%.

Q2 gold production was 1.98 million ounces at total cash costs of US$445 per ounce and net cash costs of $US338 per ounce. The company said it is on track to meet its 2011 operating guidance of 7.6-8.0 million ounces at total cash costs of US$450 to US$480 per ounce and lower expected net cash costs of US$290 to US$320 per ounce compared to previous guidance of US$340 to US$380 per ounce. Including Lumwana, Barrick expects to produce 455-475 million pounds of copper in 2011 at total cash costs of US$1.55 to US$1.70 per pound.

But Barrick also said at Pueblo Viejo, a major rainfall event that occurred in May requires remediation of the starter tailings dam and new permits for this facility. Primarily as a result of the unanticipated remediation work and impact to the schedule, mine construction capital for the project has increased to US$3.6-$3.8 billion (100% basis) or US$2.2-$2.3 billion (Barrick's 60% share) and first production is now expected to occur in mid-2012 subject to the receipt of these permits. As part of a longer term, optimized power solution for Pueblo Viejo, the company is advancing a plan to build a dual-fueled power plant at an estimated incremental capital cost of about US$0.3 billion (100% basis). The new plant is expected to provide lower cost, long term power to the project.

It added capital costs for Pascua-Lama have been impacted by continued inflationary effects on costs for key consumable inputs and labor, re- estimations of materials such as steel, cement, fuel and equipment and increased expenditures to essentially maintain the schedule to deliver first production in mid-2013. As a result, pre-production capital is now estimated at US$4.7-$5.0 billion.

The views and opinions expressed herein are the views and opinions of the author and do not necessarily reflect those of Nasdaq, Inc.

Copyright (C) 2016 MTNewswires.com. All rights reserved. Unauthorized reproduction is strictly prohibited.


The views and opinions expressed herein are the views and opinions of the author and do not necessarily reflect those of Nasdaq, Inc.

Other Topics

Commodities