Markets

Nevada Copper Announces Positive Feasibility Study Results for Stage 1 Underground Mine

Nevada Copper Corp. (NCU.TO) has filed its National Instrument 43-101 Technical Report Feasibility Study for its 100% owned Pumpkin Hollow Copper project located near Yerington, Nevada.

Highlights of the Feasibility Study (in US$):

The project development consists of a 6,500 ton-per-day underground operation at the East deposit, feeding a single 6,500 ton-per-day concentrator located near the East shaft;

First production targeted for early 2015, with an initial mine life of 12 years;

Proven and Probable Mineral Reserves (East deposit only): 823 million pounds of copper and 220,765 ounces of gold and 4.7 million ounces of silver;

The views and opinions expressed herein are the views and opinions of the author and do not necessarily reflect those of Nasdaq, Inc.

Copyright (C) 2016 MTNewswires.com. All rights reserved. Unauthorized reproduction is strictly prohibited.


The views and opinions expressed herein are the views and opinions of the author and do not necessarily reflect those of Nasdaq, Inc.

Other Topics