US Refinery Status: Exxon Restarts Baytown FCCU



DOW JONES NEWSWIRES

The following table lists unplanned and planned production outages at U.S. refineries as reported by Dow Jones Newswires. The information is compiled from both official and unofficial refining sources and doesn't purport to be a comprehensive list.

Exxon Mobil Corp. (XOM) will restart early Tuesday its No. 3 fluid catalytic cracker at Baytown, Texas, according to a state regulatory filing.

Husky Energy Inc. (HSE.T) is in the process of restarting its refinery in Lima, Ohio, the state environmental protection agency said Friday.

BP PLC (BP) reported Friday that its Texas City, Texas, refinery experienced flaring at its ultracracker, according to a filing with state environmental regulators.

The cause of the emissions event, which lasted for about one hour Friday afternoon, "is still unknown and under investigation," the filing stated. The company couldn't be immediately reached for comment.

Valero Energy Corp. (VLO) announced Friday that it is shutting down its Delaware City, Del., refinery permanently due to poor economics. On Thursday, the company's Texas City, TX, plant reported flaring due to a snag at boilers in complex 4 and restarted one of three modules that were shut earlier in the week for repairs.

For more detailed information, search Dow Jones Newswires using the code N/ REF.

Operator   Refinery    Capacity   Description                  Restart
                       (in 000s
                       bbl/day)

UNPLANNED

CANADA


Suncor     Sarnia      85.0    Hydrocracker unit shut Oct           n/a
           Ontario             11 due to fire at associated
                               compressor; no  restart esti-
                               mate available.

EAST COAST

Conoco     Linden    238.0     Officials consider run cuts      n/a
           N.J.                due to slack demand, a per-
                               son familiar with operations
                               said on July 17.

CARIBBEAN

CPC     Bayamon        48.0  Explosion, fire at facility     n/a
        Puerto Rico          early on Oct. 23. 11 out of
                             30 storage tanks exploded.

GULF COAST

BP      Texas City    455.8  SRU hit snag Oct. 26, back to normal Oct. 27
                             Co. restarts Ultraformer #4 Nov. 1
                             BP restarting ultracracker on
                             Nov. 7-19. Flares at Ultracracker
                             Nov. 20

Citgo      Corpus     163.0  Alkylation unit shut July 19        end-Oct
           Christi, TX      by near-fatal explosion to
                             return to service by end-Oct.
                             The restart was delayed from
                             early-Oct due to safety issues.
                             FCCU, restarted Oct. 29


Valero    Texas City  199.5   FCCU operating at normal rates Nov. 17
                             after being restarted over the weekend;
                             shut Oct. 25 to repair a slide valve.

                             Snag involving three boilers at
                             complex 4 resulted in flaring, Nov. 19.

Western El Paso, TX   125.0  FCCU wet gas compressor restarting
                             Nov. 19 after tripping offline.

Flint      Corpus     288.1  Found and fixed a pinhole gas leak
Hills      Christi, TX       in a crude unit pipe Nov. 19.

MIDWEST

ROCKY MOUNTAINS

Holly     Wood Cross    25.0  Brief power outage shuts units Nov. 4.
          Utah                Restarted same day.

Flying J  Salt Lake     29.4  Brief power outage shuts units Nov. 4.
          Utah                Restarted same day.

WEST COAST
Chevron   Richmond, CA   240.0  Reported mechanical snag Nov. 18;
                                warned it could result in flaring

Tesoro    Wilmington     100.0  Fuel gas system upset Nov. 14
          CA                    caused boilers, process heaters
                                and co-gen unit to release emissions.

Conoco   Rodeo, CA       120.2  Reported flaring due to a unit
                                shutdown Nov. 17; no more details.

Exxon   Torrance,CA      149.5  Reported flaring from system upset
                                Nov. 18; operations normal


PLANNED

CANADA

Irving OIl Saint John   300.0   Completed $220 million investments
                                upgrades including FCCU, diesel
                                hydrotreater, crude unit, amine units,
                                hydrogen plant, more piping, and fresh
                                catalysts, among others things, Co. said
                                Nov. 17.

CARIBBEAN

Valero     Aruba         235.0  The refinery that was shut
                                in June for 2-3 months for
                                economic reasons is being
                                closed indefinitely.

EAST COAST

Sunoco    Westville, NJ  145.0  Idling all refining              Mid-Nov
                                operations indefinitely due
                                to poor economics, Co. said
                                Oct. 6. It will take 4-6
                                weeks to work through crude
                                stocks to shut down.

                                Reformer unit shut in Girard     n/a
                                Point section in early Oct
                                for economic reasons. Shutdown
                                to last 1-6 months.

Valero     Delaware City 210.0 Plant to be permanently shut due
                               to poor economics, announced
                               Nov. 20. Delaware Official said
                               it would be shut on Nov. 22.


Western    Yorktown       64.5  Planned work scheduled 1Q 2010.
           Va.

MIDWEST
Frontier   Kansas         130.0  Extended FCCU work by several
                                 days will reduce charge
                                 rates to 76,000 bbls/day from
                                 81,500 bbls/day.

Husky     Lima Ohio         160.0  Plant Restarting.             Nov. 20

ROCKY MOUNTAIn

Western    Bloomfield,     16.8  Co. announced plans Nov. 9
           NM                    to idle plant and shift
                                 production to Gallup plant.

Western    Gallup,         20.8  Utilization will be boosted
           NM                    to near full capacity with
                                 Bloomfield shutdown, from
                                 about half, Co. said Nov. 9.

Tesoro    Salt Lake City,  58.0  Planned turnaround in 2010;
          Utah                   no timetable disclosed.

Tesoro    Mandan, N.D.     58.0  Planned turnaround in 2010;
                                 no timetable disclosed.

Exxon     Joliet, Ill.    238.6  Vacuum distillation unit restarted
                                 earlier this week after planned
                                 work, Co. said Nov. 11.

GULF COAST

Alon       Krotz Springs  80.0  Plantwide turnaround starts      Nov. Dec.
           LA.                  In Nov.

Alon       Big Spring,    67.0  Restarted SRU on Nov. 6.
           TX

Chevron    Pascagoula,   330.0  Pre-commercial heavy oil         2010
           Miss.                conversion project delayed
                                from 2008 to 2010 due to
                                economic factors.

Conoco    Borger, TX     146.0  Unidentified units shut for
                                planned turnaround, Co. said
                                Oct. 9. No further details.
                                Shut amine unit for planned     Oct. 24
                                maintenance Oct. 9-24.

                                Shut Unit 34 SRU and tail gas   Nov. 15
                                treatment unit for planned
                                repairs Nov. 12-15.

Conoco     Sweeny, TX    247.0  Six weeks of turnaround work     Oct 30
                                starts Sept. 14 at Units 14,
                                9, 38 and 27, which is an
                                FCCU.

                                FCCU leak being repaired Nov. 12.

                                Tail gas incinerator shut during  Nov. 1
                                fall turnaround Sept. 30

Exxon      Baytown       572.5  FCCU No. 3 shut Sep 15. for       Nov. 24
           TX                   planned maintenance. Restarted

Nov. 24

Flint      Corpus        288.1  $250 mln project for new         Spr
Hills      Christi, TX          diesel desulfurization,          2010
                                sulfur recovery unit to begin
                                in Fall 2008. Construction
                                to last 18 months.

Marathon   Garyville     245.0  Project to increase crude oil    4Q
           LA                   refining capacity by 180,000-    2009
                                b/d 85% complete, as of end
                                April. New units expected
                                start up in 4Q 2009. Entire
                                refinery reaches full capacity 2Q'10

Motiva     Port Arthur   285.0  Expansion project to increase    1Q
           TX                   throughput capacity by 325,000   2012
                                b/d, to 610,000-b/d, slowed.
                                Completion now seen 1Q
                                2012, from 2010.



Valero   Port Arthur  310.0    Shut all three modules of 105,000
         TX                    bpd coker to repair cracks in coke
                               drums, and to be returned to service
                               over next several days Co. said
                               Nov. 17. Restarted one coker module
                               Nov. 19.

Valero     Corpus        340.0  Coker unit shutdown for econo-   n/a
           Christi, TX          mic reasons and planned work;
                                delayed to June 19 from June
                                12. The 20,000-b/d unit will
                                remain off line through July
                                but could restart at any time
                                if margins improve.

                                20,000-b/d FCCU in East          n/a
                                Plant shut; West Plant
                                50,000-b/d FCCU at reduced
                                rates since mid-Dec for
                                economic reasons.

                                15,000-b/d HCU in East Plant
                                set for 18 days of work in Jan.

                                36,000-b/d HCU in West Plant
                                sent for 18 days of work in Feb.

                                Restarting West Plant Tank 67
                                after maintenance, Nov. 12-13.

Valero     Norco, LA     250.0  Upgrade project to build         2012
                                a new diesel hydrotreater
                                unit moved from 2010 to
                                4Q 2012.

                                Turnaround at crude/ coker unit    1Q
                                set for 36 days in Jan.
                                Entire Plant
                                to be shut for work.

                                The coker will operate at
                                50% of capacity when
                                restarted due to poor
                                economics.

Valero     Port Arthur   325.0  77,000-b/d FCCU at reduced       n/a
           TX                   rates since mid-Dec for
                                economic reasons.

                                45,000 b/d HCU to undergo        Spring
                                38 days of work in March.

Valero     Sunray, TX    170.0  55,000-b/d FCCU at reduced       n/a
                                rates since mid-Dec for
                                economic reasons.

Western    El Paso, TX    29.5  Planned work at south side of
                                plant, including crude unit
                                and FCCU in Jan for 20 days.

WEST COAST


Tesoro    Golden Eagle   166.0  40 days of work, including FCCU,    Feb.
                                alky starting Jan. 8

Tesoro     Wilmington    100.0  Restarting hydrocracker Nov. 9. It
           CA                   will take several days.
                                Unplanned downtime at the delayed
                                coker will impact 4Q yields, co.
                                said Nov. 9. Coker was restarted
PACIFIC

Tesoro    Oahu, HI        94.0  Planned turnaround in 2010;
                                no timetable disclosed.
--


  (MORE TO FOLLOW) Dow Jones Newswires
  11-24-090845ET
  Copyright (c) 2009 Dow Jones & Company, Inc.