Tahoe Resources Reports Q1, Updates on Escobal and Five Year Plan; Shares Fell 3.5% Thursday

By
A A A

Tahoe Resources Inc. (THO.TO, TAHO), which fell 3.5% Thursday, today reported financial results for the quarter ending March 31, 2013, and provided updates regarding its flagship Escobal silver project in Guatemala and the company's Five Year Plan, which was updated to reflect royalty and loan repayment.

It said: Projected spending differences are largely due to timing of Escobal project expenditures and payments. The project remains on time and on budget. Capital spending projected for 2014 through 2017 is a combination of sustaining capital and the 4,500 tpd expansion project. Assuming $25 per silver ounce; a full draw on the $50 million credit facility; payment of interest expenses; and the new 5% NSR mining royalty.

Financial Highlights for the first quarter of 2013 include (stated in U.S. dollars):

Net earnings/(loss) for the quarter amounted to ($24.9 million) or ($0.17) per share.

Cash outflow from operating activities amounted to $28.0 million.

Corporate G&A expense amounted to $3.4 million, excluding non-cash share-based compensation of $1.3 million.

Exploration expenses amounted to $1.3 million.

A project-to-date total of $288.7 million of the $326.6 million budget has been spent towards construction of the 3,500 tonne per day (tpd) Escobal project.

Cash and equivalents at quarter-end were $107.2 million.

Escobal Project Update: The construction and underground development of the Escobal project is continuing on-schedule and on budget. Engineering, procurement and construction management was at 79% completion and underground development necessary for commencement of production was at 90% completion as of March 31, 2013. The company completed 1,937 metres of underground development during the first quarter and 7,144 metres to date.

Mill commissioning is projected to begin in the second half of 2013 with commercial production expected in early 2014. All major components are in place, and the focus has turned to piping and electrical systems in the mill, completion of steel erection, conveyor installation and civil engineering work at the tailings facility. Dry commissioning of the crusher and milling circuit is expected to take place in the second quarter.

Underground work has been expanded to primary stope development. Numerous vein cross-cuts on the 1290 and 1265 levels have been established, and drilling of the first slot raises and stope blastholes are underway. Rock conditions in the production areas are as projected in the model defined in the May, 2012 Preliminary Economic Analysis (PEA).



The views and opinions expressed herein are the views and opinions of the author and do not necessarily reflect those of The NASDAQ OMX Group, Inc.

Copyright (C) 2014 MTNewswires.com. All rights reserved. Unauthorized reproduction is strictly prohibited.


This article appears in: Investing , Commodities

Referenced Stocks:

MT Newswires

MT Newswires

More from MT Newswires:

Related Videos

Stocks

Referenced

Most Active by Volume

112,131,130
  • $74.98 ▲ 5.18%
57,963,905
  • $8.32 ▲ 8.33%
48,392,602
  • $3.45 ▼ 0.29%
45,276,527
  • $36.17 ▲ 4.21%
44,800,927
  • $17.84 ▲ 0.34%
44,539,649
  • $97.03 ▼ 0.16%
44,078,180
  • $15.62 ▲ 0.64%
43,461,551
  • $35.50 ▼ 1.06%
As of 7/24/2014, 04:04 PM